Crombie Inc. uses a job-order costing system in which any underapplied or overapplied overhead is closed out to cost of goods sold at the end of the month. The company has provided the following data for June:
Direct materials $ 46,500
Direct labor cost 76,500
Manufacturing overhead cost incurred $ 69,750
Manufacturing overhead cost applied $ 74,560
Inventories: Beginning Ending
Work in process $17,500 $27,840
Finished goods $69,080 $35,700
The unadjusted cost of goods sold (in other words, cost of goods sold before adjusting for any underapplied or overapplied overhead) for June is closest to:
$197,560
$215,790
$187,220
$220,600