Which analysis costs has highest expected monetary value


Clarkson Products, Inc., of Clarkson, New York, has the option of (a) proceeding immediately with production of a new top-of-the-line stereo TV that has just completed prototype testing, or (b) having the value analysis team complete a study. If Ed Lusk, VP for operations, proceeds with the existing prototype (option a), the firm can expect sales to be 100,000 units at $550 each, with a probability of 0.6; and a 0.4 probability of 75,000 units at $550. If, however, he uses the value analysis team (option b), the firm expects sales of 75,000 units at $750, with a probability of 0.7; and a 0.3 probability of 70,000 units at $750. Value analysis costs $100,000 and is only used in option b. Which option has the highest expected monetary value (EMV)?