Given the following:
Activity
|
Crash Time (days)
|
Crashed Cost (total)
|
Normal Time (days)
|
Normal Cost
|
A: Obtain Instructor
|
4
|
$800
|
7
|
$500
|
B: Locate a Room
|
2
|
350
|
3
|
200
|
C: Check Costs
|
4
|
900
|
6
|
500
|
D: Room Open?
|
1
|
500
|
3
|
200
|
E: Schedule Class
|
1
|
550
|
2
|
300
|
1. Find the crash cost per day
2. Which activities should be crashed to meet a project deadline of 10 days with a minimum cost? Assume partial crashing is allowed.
3. Find the new cost
4. Is partial crashing an appropriate assumption in this kind of project?