Problem:
Schedule the following activities using CPM: |
|
|
|
Activity |
Immed. Precessor |
time (weeks) |
A |
|
1 |
B |
A |
4 |
C |
A |
3 |
D |
B |
2 |
E |
C, D |
5 |
F |
D |
2 |
G |
F |
2 |
H |
E, G |
3 |
Required:
Question 1) Draw the network.
Question 2) What is the critical path?
Question 3) How many weeks will it take to complete the project?
Question 4) Which activities have slack, and how much?
Solve the given numerical problem and illustrate step by step calculation.