When should raw material be reordered in acceptable risk


A shop owner uses a reorder point approach to restocking a certain raw material. Lead time is six days. Usage of the material during lead time is normally distributed with a mean of 42 pounds and a standard deviation of 4 pounds. When should the raw material be reordered if the acceptable risk of a stockout is 3%?