At an activity level of 9,200 machine-hours in a month, Smith Company's total variable production engineering cost is $761,300 and its total fixed production engineering cost is $154,008. What would be the total production engineering cost per unit, both fixed and variable, at an activity level of 9,300 machine-hours in a month? Assume that this level of activity is within the relevant range.