Question: Carol has recently joined the team as the project manager for a project strict on budget. Over the past one month of planning, she's told you on multiple occasions about the number of changes to the requirements of her project and the subsequent headaches that she endures to get the baselines aligned to the minute detail. Which of the following would be the best advice that you could give her? A. Adjust the scope, schedule and cost baselines in a way that reduces her work B. Accommodate the changes to ensure only one baseline is affected C. Adjust scope and schedule baselines within cost constraints D. Delegate the tasks of aligning the baselines whenever there are changes