What will be the idle time at the fourth workstation of the


RS Corp. is designing a product layout for a new product. They plan to use this production line ten hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product: Task Time (Secs) Immediate Predecessor a 34 none b 20 a c 10 b d 16 b e 10 c f 24 d,e g 38 f

For output to equal forecasted demand, what will be the idle time at the fourth workstation of the assembly line that uses the least number of workstations?