What will be maximum inventory level between the two steps


Problem

A two-step production process has a daily quota of 100 units. The first step has a cycle time of 0.25 min/unit. Since the second step is the bottleneck, inventory grows at 2 units/minute while both steps are producing. What will be the maximum inventory level between the two steps while they produce the daily quota of parts?