Messersmith Company is constructing a building. Construction began in 2010 and the building was completed 12/31/10. Messersmith made payments to the construction company of $1,000,000 on 7/1, $2,100,000 on 9/1, and $2,000,000 on 12/31. what were Average accumulated expenditures ?