During March, Younger Company's direct material costs for product T were as follows:
Actual unit purchase price	$6.50 per meter
Standard quantity allowed for actual
production	2,100 meters
Quantity purchased and used for actual
production	2,300 meters
Standard unit price	$6.25 per meter
what was the Younger's material quantity variance for March ?