The company applies overhead on the basis of direct labor cost. Only one job was steill in process on May 31. The job had $75,450 in direct material and $36,200 in direct labor cost assigned to it.
a. What was the predetermined overhead application rate?
b. What was the balace in WIP Inventory at the end of May?
c. What was the total cost of jobs completed in May?