The standards for product C54L specify 4.5 DLH per unit @ $12.40 per DLH. Last month 1,560 units of product C54L were produced using 7,000 direct labor-hours at a total direct labor wage cost of $86,100.
a. What was the labor rate variance for the month?
b. What was the labor efficiency variance for the month?