What was the direct labor quantity variance


The standard direct labor cost for producing one unit of product is 5 direct labor hours at a standard rate of pay of $8. Last month, 5,000 units were produced and 24,500 direct labor hours were actually worked at a total cost of $180,000.what was the direct labor quantity variance ?