The Pathway Company had budgeted direct labor costs of $1,600,000 manufacturing overhead of $800,000, and allocated based on direct labor costs. If actual direct costs were $1,500,000 and actual manufacturing costs were $770,000, what was the amount of overapplied or underapplied overhead?