What stage of schedule management does decision fall under


Question: "Halfway through a project, a project manager learns that a task will take longer than expected. In response, the project manager reorganizes the schedule and sets a new baseline for the project. What stage (and PMBOK® Guide Process) of schedule management does this decision fall under? "Control Schedule Estimate activity durations Plan schedule management Develop schedule

 