What should you as purshasing agent expect to pay for the


It took an international shipyard 135000 labor hours to produce the first of several tugboats that you expect to purshase for your shipping company, Great Lakes, Inc. Boats 2 and 3 have been produced by the international shipyard with a learning factor of 80%. At 40$ per hour, what should you, as purshasing agent, expect to pay for the fourth unit ? how long will all four boats require ?