What should the scrum master do next


Question: During a demonstration, the product owner asked the team to add new scope to the backlog. Which of the following should the Scrum master do NEXT? A. Create a change request for the change advisory board. B. Work with the business analyst to document the new epic. C. Reject the change to prevent scope creep. D. Update the risk register and the work in the mitigation plan.

 