What should the project manager do next


Problem:

At the end of a project, one of the suppliers is facing financial difficulties and is pushing the project manager to obtain financial, legal, and administrative approval in order to communicate formal project closure and ensure the transfer of liability. What should the project manager do next?

  • Transfer the remaining variances and close the project.
  • Compare the achieved results to the contract requirements.
  • Escalate to higher management to expedite the approval.
  • Make the final payment as the project is completed.

 