Question: As a result of an approved change request, the project manager updates the project plan to reflect the new feature addition and the revised production release date. Which of the following change control processes should the project manager do NEXT? A. Validate the change implementation. B. Implement the change. C. Conduct an impact assessment. D. Communicate the change deployment.