Problem: After realizing that there are insufficient resources on a project that has an increasingly high workload, management outsources some major tasks to keep the project on schedule. What should the project manager do in this scenario? SELECT THE CORRECT ANSWER Review the communications management plan Revise the procurement management plan Escalate to the project sponsor Prepare an organizational chart