Question: There is a chance that a mechanical component will break, and this will lead to the failure of a quality requirement. This nonfunctional requirement is critical for the customer to accept the final deliverable. No one thought this would be possible. What should the project manager do? This type of question contains radio buttons and checkboxes for selection of options. Use Tab for navigation and Enter or space to select the option. Option A Implement a change control request to adjust the schedule and scope. Option B Immediately instruct the team to implement a fix before the component fails. Option C Add this to the risk register to assess its impact and probability. Option D Review the requirements traceability matrix.