Problem: The project manager is reviewing the Cost Performance Report. She notices that the 50/50 Rule was applied to a work activity that is 40 work days in duration. What should the project manager do?
Group of answer choices
A. Have the Earned Value recalculated using the 0/100 Rule since the activity is 40 workdays in length.
B. Have the Earned Value recalculated using the Milestone Weights method since the activity is greater than 20 workdays in length.
C. Have the Earned Value recalculated using the Percent Complete method since the activity is 40 days or less in length.
D. Nothing. The rule is accurately applied.