A firm wants to develop a level material use schedule based on the following data. What should be the setup cost?
Desired lot size: 60
Annual demand: 40,000
Holding cost: $20 per unit per year
Daily production rate: 320
Work days per year: 250
a)$0.45
b)$4.50
c)$45
d)450
e)$500