It is common for activities in projects to run late. What should be DONE when this happens differs between traditional Critical Path Method (CPM) and TOC’s Critical Chain Project Management (CCPM). The upper-most of the two diagrams that follow is a typical CPM Gantt Chart schedule/layout. The lower of the two diagrams is a typical CCPM schedule (with resource, feeding and project buffers included).