What range of output is theoretically possible for the line


An assembly line with 17 tasks is to be balanced. the longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. the line will operate for 450 minutes per day.

1. what is the minimum number of workstation needed if the maximum output rate is to be sought?
2. what range of output is theoretically possible for the line?