What project should the alliance accept


Assignment:

Year    Project A Project B
0    -$250,000    -$400,000
1    $100,000    $50,000
2    $80,000    $70,000
3    $60,000    $80,000
4    $40,000    $120,000
5    $20,000    $200,000

The above are two mutually exclusive investment projects for Rebel Alliance. The Alliance requires getting their invested amount fully paid back within 5 years. The Alliance's cost of capital (i.e., the required return on investment) is 6% annually.

1. Based on the Payback rule, what project(s) should the Alliance accept?

a.    Project A only.
b.    Project B only.
c.    Both Projects A and B.
d.    Neither Project A or B.

2. Based on the NPV rule, what project(s) should the Alliance accept?

a.    Project A only.
b.    Project B only.
c.    Both Projects A and B.
d.    Neither Project A or B.

3. Based on the IRR rule, what project(s) should the Alliance accept?

a.    Project A only.
b.    Project B only.
c.    Both Projects A and B.
d.    Neither Project A or B.

4. Based on your answers to Q8-10, what project(s) should the Alliance accept?

a.    Project A only.
b.    Project B only.
c.    Both Projects A and B.
d.    Neither Project A or B.

5. At what discount rate would the Alliance be indifferent between the two projects?

a.    4%.
b.    5%.
c.    6%.
d.    7%
e.    8%.

Solution Preview :

Prepared by a verified Expert
Finance Basics: What project should the alliance accept
Reference No:- TGS01815239

Now Priced at $20 (50% Discount)

Recommended (97%)

Rated (4.9/5)