Question: Monitoring contractor performance includes a review of progress reports. Which item should the COR not check for in a progress?
a) Whether the expenses match the amount of work performed so far
b) Whether the contractor is on schedule
c) Whether the individual contractor employees are performing to contract standards
d) Whether actual deliveries match what is in the report