What minimum displayed green time must be provided to


A left-turn movement has a maximum arrival rate of 200 veh/h. The saturation flow of this movement is 1400 veh/h. For this approach, the yellow time is 4 seconds, all red time is 2 seconds, and total lost time is 3 seconds. The cycle length is 120 seconds.

What minimum displayed green time must be provided to ensure that the queue in each cycle clears, and what is the total delay per cycle and delay per vehicle for this green time? (Assume D/D/1 queuing.)

Request for Solution File

Ask an Expert for Answer!!
Other Engineering: What minimum displayed green time must be provided to
Reference No:- TGS01525555

Expected delivery within 24 Hours