Question: You manage a construction site for a developer. The construction takes twenty-six week with 500 workers to build a small apartment complex. The cost are as follows, materials $32 million, overhead $2 million, labor $40 per hour including benefits and workers work 40 hours per week. The finished apartment complex sells for $75 million. What is your multifactor productivity?

 