Assignment:

Johnson Cogs wants to set up a line to serve 60 customers per hour. The work elements and their precedence relationships are shown in the following? table:
A. What is the theoretical minimum number of workstations? ___stations
B. How many stations are required using the longest work element decision rule?
C. Therefore, its efficiency is ___%.