Problem:
You have determined the critical path in a CPM analysis. You would like to determine the probability of completing the project is a desired period of time. One of the activities on the critical path has an optimistic time of 5 minutes, a most likely time of 6, and a pessimistic time of 17.
Required:
Question 1) What is the variance estimate of this activity? Solve the problem and show all work.