Problem
Jupiter Company applies overhead based on machine hours. The variable overhead standard is 24 hours at $32.00 per hour. During February, Jupiter Company spent $339,460 for variable overhead and 10,150 machine hours were used to produce 400 units. What is the variable overhead rate variance?