Southern Alliance Company needs to raise $26 million to start a new project and will raise the money by selling new bonds. The company will generate no internal equity for the foreseeable future. The company has a target capital structure of 65 percent common stock, 11 percent preferred stock, and 24 percent debt. Flotation costs for issuing new common stock are 10 percent, for new preferred stock, 8 percent, and for new debt, 3 percent. What is the true initial cost figure Southern should use when evaluating its project? (Do not round your intermediate calculations.)