Q: Shirley Hopkins is developing a program in leadership training for middle-level managers. Shirley has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors and times appear in the accompanying table:
Activity
|
Immediate Predecessor(s)
|
Time (days)
|
A
|
-
|
2
|
B
|
-
|
5
|
C
|
-
|
1
|
D
|
B
|
10
|
E
|
A, D
|
3
|
F
|
C
|
6
|
G
|
E, F
|
8
|
What is the total project completion time?
What is the slack time for each individual activity?