Assignment:

Q: Shirley Hopkins is developing a program in leadership training for middle-level managers. Shirley has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors and times appear in the accompanying table:

Activity

Immediate Predecessor(s)

Time (days)

A

-

2

B

-

5

C

-

1

D

B

10

E

A, D

3

F

C

6

G

E, F

8

What is the total project completion time?

What is the slack time for each individual activity?