What is the total manufacturing cost assigned to job 413


a) A company assigns overhead cost to completed jobs on the basis of 120% of direct labor cost. The job cost sheet for Job 413 shows that $12,000 in direct materials has been used on the job and that $8,000 in direct labor cost has been incurred. A total of 200 units were produced in Job 413.

Required:

1. What is the total manufacturing cost assigned to Job 413? What is the unit product cost for Job 413? 

Solution Preview :

Prepared by a verified Expert
Managerial Accounting: What is the total manufacturing cost assigned to job 413
Reference No:- TGS01271907

Now Priced at $15 (50% Discount)