An analysis of past maintenance costs indicated that maintenance costs is an average of $0.20 per machine hour at an activity level of 10,000 machine hours and $0.25 per machine hour at an activity level of 8,000 machine hours. Assuming that this activity is within the relevant range, what is the total expected maintenance cost of the activity level is at 8,700 machine hours?