Vehicles begin to arrive at a parking lot at 6:00 A.M. with an arrival rate function (in vehicles per minute) of λ(t) = 1.2 + 0.3t, where t is in minutes. At 6:10 A.M. the parking lot opens and processes vehicles at a rate of 12 per minute.
What is the total delay and the maximum queue length?