What is the total cost of the project


Assignment Problem:  Crashing Project

A company is faced with the following project. The project has indirect costs of $1,000 per day. What is the most economical duration of the project? What is the total cost of the project?

Activity

Immediate Predecessors

Normal Duration

Normal Duration Total Cost

Minimum Duration

Minimum Duration Total Cost

A

-

10

$12,000

5

$16,000

B

A

20

$15,000

15

$18,250

C

B

25

$8,000

15

$12,000

D

B

20

$9,000

15

$12,500

E

C, D

15

$20,000

13

$21,800

F

E

15

$11,000

10

$16,250

G

A

60

$25,000

45

$29,500

H

F, G

5

$4,200

4

$5,050

 

 

Request for Solution File

Ask an Expert for Answer!!
Project Management: What is the total cost of the project
Reference No:- TGS03055794

Expected delivery within 24 Hours