Mighty Corporation manufactures end tables. Each end table requires 4 direct labor hours for each table. Mighty Corporation has a direct labor rate of $18 per direct labor hour. The production budget shows that Mighty Corporation plans to produce 1493 end tables in March and 1559 end tables in April. What is the total combined direct labor cost that should be budgeted for March and April?