Problem
Mighty Corporation manufactures end tables. Each end table requires. 50 direct labor hours in its production. Mighty Corporation has a direct labor rate of $15 per direct labor hour. The production budget shows that Mighty Corporation plans to produce 1,000 end tables in March and 1, 100 end tables in April. What is the total combined direct labor cost that Mighty Corporation should budget in March and April?