Hart Manufacturing operates an automated steel fabrication process. For one operation, Hart has found that 46% of the total throughput time is spent on non-value-added activities. Delivery cycle time is 20.40 hours, waiting time during the production process is 5.00 hours, queue time prior to starting the production process is 3 hours, and inspection time is 1.4 hours.What is the throughput (manufacturing cycle) time for the operation?