Assignment:
Q: The questions are based on the information below
Inspection time
(3 minutes )
|
WIP 1 |
Assembly
(2 minutes)
|
WIP 2 |
Dispatch
(6 minutes)
|
Scenario
Work arrives at a plant at the rate of 30 customers per hour from 11AM -1 PM. They continue to wait till such time they are served.
What is the cycle time for the process?
What is the throughput rate of the process?
What is the process capacity?
What is the maximum build up in WIP 2?
Approximately, what time is the dispatch stage completing work?