Problem: You are the PM on a project to construct 20 miles of sidewalk. Your plan indicates a cost of $15,000 per mile and will take 8 weeks to complete. 3 weeks into the project you have completed 8 miles of sidewalk at a cost of $115,000. What is the TCPI?