Takt time question:
Task Time
A 45 min.
B 50 min.
C 40 min.
D 55 min.
E 40 min.
F 65 min.
G 25 min.
H 35 min.
For this exercise, don't worry about task predecessors.
The working day is seven hours.
The required output is 360 units per day (per seven hour working day).
What is the takt time?
What are the minimum number of workstations needed?
What is the idle time?
What is the percent idle time?
What is the efficiency delay?