What is the takt time of the manufacturing cell and what is


For this assignment, you will be required to read the following prompt and chart and answer the questions that follow.

Yahoo Widgets, Inc. (YWI) is a widget manufacturer in Williamsburg, Virginia. YWI receives raw material sheets of plastic from Tribe Plastics, once per week, on Monday, for the family of widget models it produces. These widgets are then shipped to another manufacturer, Acme Gadgets, Inc. (AGI), for inclusion in its family of gadgets, which are sold to end users. For its new product line, the gadget manufacturer requires two types of widgets, large and small, that are packaged in returnable trays holding 55 widgets for shipment. The trays are returned, empty, to YWI after the widgets are used by AGI. The manufacturing process consists of a thermoforming activity that transforms the sheets of plastic into a "rough" widget, which requires a drilling process step and a grinding and sanding process step before the packing and shipping process step. These steps and related information are shown in the following table.

Process Characteristics

Average Demand: 5000 per day, 3500 large, 1500 small Batch size: 1100

Number of shifts per day 2

Shift 8 hours with 30 minute lunch

Process Step 1

Thermo-form

Cycle time = 15 seconds

Set-up tine =15 minties

Up time= 85%

Operators = 2

Every part every week

WIP = 5 days of sheets n front of Thermo-forming machine

Process Step 2

Drill

Cycle time = 32 seconds

Set-up tine = 25 minutes Up trne= 80%

Operators = 4

Every Part every week

WIP = 1250 large, 1500 small

Process Step 3

Orin, Sand

Cycle time = 22 seconds

Set-up time = 27 minutes

Up time= 75% Operators = 5 Every part every week

WIP = 1750 large, 1250 smell

Process Step 4

Pack and Sly

WIP = 750 large, 125 sma

Shipments

One shipment of 5000 per day

Information Flow

Electronic commtrication of forecasts to supplier

Electronic communication of daly orders from customer

Electronic communication of forecasts from customer

Electronic cornmunicabon of daly slipping schedule to process step 4 Electronic cornrnunicabon of weekly schedule to process steps 1-3.

All materiel is notched

1. Using the data shown in the table above, construct a value stream map for Yahoo Widgets, Inc.

2. What is the takt time of the manufacturing cell?

3. What is the production lead time for each process step?

4. What is the total processing time for the manufacturing cell?

5. What is the total capacity of the manufacturing cell?

Requirements
USE VSM Template
- Show

o Critical thinking

o Original thinking
- Use direct quotations sparingly and judiciously
- Properly identify any sources and integrate into own thoughts and ideas
- Provide a straightforward, easy-to-follow arrangement with appropriate formatting:

o Comply with APA format
- Create an Excel document assignment"
- 300 words Answer 2-5 short intro/short conclusion on value stream provide link to sources

Attachment:- VSM Template.rar

Solution Preview :

Prepared by a verified Expert
Operation Management: What is the takt time of the manufacturing cell and what is
Reference No:- TGS02193445

Now Priced at $10 (50% Discount)

Recommended (93%)

Rated (4.5/5)