--%>

What is the slack time-non-critical paths


Assignment:

The QuickBuild Construction Company is building a house in the suburb of Oxford, AL. They have the following list of activities, precedence, and (very optimistic, almost fixed) durations for the project.

Activity Predecessors Duration (days)
a. Excavation - 5
b. Pour Foundation A 2
c. Outside Plumbing A 12
d. Framing - 3
e. Wiring B 5
f. Roofing D 1
g. Brickwork B 7
h. Cover Walls C,E 2
i. Exterior Finishing G,F 10
j. Landscapign H,I 6

What is the slack time (in days) associated with any and all non-critical paths through the project?

If activity C were delayed by two time units, what would happen to the entire project duration? Explain. (Show all work with calculation for ES, EF, LS and LF).

Request for Solution File

Ask an Expert for Answer!!
Project Management: What is the slack time-non-critical paths
Reference No:- TGS02057547

Expected delivery within 24 Hours