Get the step by step solution to this homework question now:
Shirley Hopkins is developing a program in leadership training for middle managers. Shirley has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table.
ActivityImmediate PredecessorTime (Days)
A - 2
B - 5
C - 1
D B 10
E A,D 3
F C 6
G E,F 8
a.Develop an AON network for this problem.
b.What is the critical path?
c.What is the total project completion time?
d.What is the slack time for each individual activity?