Assignment
1. Draw a project network from the following information. What activity(s) is a burst activity? What activity(s) is a merge activity?
ID
|
Description
|
Predecessor
|
A
|
Order review
|
None
|
B
|
Order standard parts
|
A
|
C
|
Produce standard parts
|
A
|
D
|
Design custom parts
|
A
|
E
|
Software development
|
A
|
F
|
Manufacture custom parts
|
C,D
|
G
|
Assemble
|
B,F
|
H
|
Test
|
E,G
|
2. You are managing a product upgrade project for Bangkokagogo. Given the project network that follows, complete the forward and backward pass, compute activity slack, and identify the critical path. Use this information to create a Gantt chart for the project. Be sure to show slack for noncritical activities.
The critical path is?
|
|
|
What is the Slack for C?
|
|
|
What is the Slack for D?
|
|
|
What is the Slack for E?
|
|
|
What is the Slack for F?
|
|
|
What is the Length of the project?
|
|
Time periods
|
3. From the following information, compute the early, late, and slack times for each activity. Identify the critical path.
ID
|
Task
|
Duration
|
Predecessor
|
Additional Lag Relationships
|
Lag
|
A
|
Design
|
5
|
|
|
|
B
|
Order Parts
|
1
|
A
|
Start-start A to B
|
4
|
C
|
Code Software
|
6
|
A
|
|
|
D
|
Assemble
|
3
|
B
|
Finish-start B to D
|
3
|
E
|
Debug
|
3
|
C
|
Start-start C to E Finish-finish C to E
|
2 2
|
F
|
Install
|
1
|
E,D
|
|
|
The critical path is
|
|
|
What is the ES for activity C?
|
|
|
What is the KF for activity E?
|
|
|
What is the Slack for the start of activity C?
|
|
|
What is the Slack for the start of activity E?
|
|
|
What is the Slack for the end of activity E?
|
|
|
What is the Length of the project?
|
|
Time periods
|
4. From the following information, draw the project network. Compute the early, late, and slack times for each activity. Identify the critical path.
ID
|
Task
|
Duration
|
Predecessor
|
Additional Lag Relationships
|
Lag
|
A
|
Design kitchen
|
3
|
|
|
|
B
|
Tear down
|
3
|
A
|
Start-start A to B
|
2
|
C
|
Order appliances
|
1
|
A
|
|
|
D
|
Build cabinets
|
7
|
A
|
|
|
E
|
Install cabinets
|
2
|
B, D
|
Start-start D to E Finish-finish D to E
|
5 1
|
F
|
Install appliances
|
2
|
C, E
|
Finish-start C to F
|
5
|
G
|
Inspect
|
1
|
F
|
|
|
The critical path is
|
|
|
What is the ES for activity D?
|
|
|
What is the LF for activity E?
|
|
|
What is the Slack for the start of activity E?
|
|
|
What is the Slack for the end of activity E?
|
|
|
What is the Slack for the end of activity B?
|
|
|
What is the Length of the project?
|
|
Time periods
|