A project consists of two tasks. Task A is scheduled to begin at the start of Week 1 and finish at the end of Week 4. Task B is scheduled to begin at the start of Week 2 and finish at the end of Week 3. The budgeted cost for Task A is $80,000, and for Task B is $40,000.
1. Creat a cost loaded for this project:
Round the number to the closest integer number and input it without "$" and ',' signs.
Cost at Week 1:
Cost at Week 2:
Cost at Week 3:
Cost at Week 4:
2. At the end of the second week Task A is 50% complete, and Task B is 25% complete. Calculate the following items:
BCWS :
BCWP :
3. What is the schedule performance index for the project at the end of the second week (Round decimal numbers to 2 decimal places. If it is less than 1, write it in the following format: 0.xx)?
4. The actual cost of the work performed at the end of the second week is $40,000. Determine the cost performance index for the project (Round decimal numbers to 2 decimal places. If it is less than 1, write it in the following format: 0.xx).